When it comes to planning a project, the work breakdown structure is one of the first things a project manager has to work on.
In this guide, we will explain what is a work breakdown structure (WBS), how to create one, and provide you with some examples.
A work breakdown structure is a popular project management tool. It’s a diagram that helps break down large projects into smaller and more manageable parts which contain the project deliverables or outcomes that it will complete.
It’s a deliverables-oriented breaking down of a project that divides project deliverables into sub-deliverables and work packages which define the work, duration, and costs for the tasks that need to be carried out.
It has a hierarchical structure. Usually, it’s better to have three levels of decomposition in a WBS. In the case of a more complex project, you may add a fourth and a fifth level.

Following are the elements of a work breakdown structure and the common terms that you may come across when creating one.
Work packages: These are the lowest parts of a work breakdown structure. They define the work, duration, and costs for the tasks that need to be carried out to complete the deliverables. They shouldn’t be dependent on other work packages and should not exceed more than 10 days to complete.
Deliverables: Outcomes of the activities or the products or measurable outcomes you’ll have created at the end of each milestone.
Following are the principles you need to adhere to when designing a work breakdown structure.
The 100% rule: This rule helps the manager to ensure that all project efforts are captured and nothing unrelated is included in the structure. According to it the sum of the “child” tasks (on any level) must equal to 100% of the parent tasks.
All deliverables and sub-deliverables must be mutually exclusive, which means they shouldn’t appear twice within the work breakdown structure. This helps avoid miscommunication and duplication of tasks.
The 8/80 rule: According to this rule, the work packages or the work required to create the deliverables should not take less than eight hours and more than eighty hours.
The work breakdown structure must be focused on outcomes or deliverables and not the activities you need to complete to get there. Focus on the what and not the how.
Following we have listed the steps you need to take to create a work breakdown structure from scratch.
Step 1: Get your team together to identify the deliverables and sub-deliverables of the project. This would include the project managers and the subject matter experts.
Step 2: Gather the necessary documents such as the project charter, project scope statement, and project scope management plan.
Step 3: Identify the key deliverables of the project. These should come at the second level of your WBS. Key deliverables will be essential to the completion of the project and they will be carried out by independent teams – meaning the same team won’t be working on completing another deliverable.
Step 4: With the help of the subject matter experts, break the key deliverables into smaller parts of work (work packages) or in other words identify the work that is necessary to complete each deliverable.
Step 5: Create a WBS dictionary which is a document that includes the definition and the scope of the different elements in your work breakdown structure. The WBS dictionary would include information such as work package name and ID, name of the person it is assigned to, due date, estimated cost, etc. This will help the team understand work packages better.
Step 6. You can create a WBS using different formats like text-based work breakdown structures, tabular structures, or more visual ones like flowcharts. Once it is complete, share it with the team.
Work Breakdown Structure Templates